Viet Chao Joint Stock Company is honored to provide the automated parking system for the MB Sunny project at Sunny Building in District 1, Ho Chi Minh City.

Exterior of MB Sunny Tower in Ho Chi Minh City
Exterior of MB Sunny Tower in Ho Chi Minh City
  • Address: 259 Tran Hung Dao Street, District 1, Ho Chi Minh City

  • Brand/model: XIZI – 51 parking spaces (PSH2 – 49 spaces and MINI 31A – 1 system / 2 spaces)


MB Sunny project: project information

Located on Tran Hung Dao Street, MB Sunny Tower is part of a chain of office buildings for lease in District 1. Tran Hung Dao is a major two-way street connecting District 5 and District 1. Thanks to its strategic location, the building is close to District 1’s commercial, service, and administrative center, just approximately a three-minute drive from Ben Thanh Market. The surrounding area attracts a large number of foreign residents and visitors and features numerous hotels, restaurants, cafés, and other office buildings. From this location, customers can also easily access Districts 3, 4, 5, 6, 7, 8, and 10.
The purpose of installing an automated parking system is to provide a convenient parking solution while controlling vehicle entry and exit to ensure maximum security. This helps improve the quality of life and enhance convenience for building occupants.

Challenges posed by the investor

  • Installation address: 259 Tran Hung Dao Street, District 1, Ho Chi Minh City

  • Project: Residential building combined with commercial services

  • Scope of work: Design, supply, and installation of the automated parking system

  • Implementation year: 2015

  • Investor requirements:

Viet Chao’s proposed solution

  • Brand: XIZI iParking

  • Model: Puzzle-type automated parking system PSH-2 and PJS2 lifting-type parking system

  • Parking capacity: XIZI – 51 spaces (PSH-2 – 49 spaces and MINI 31A – 1 system with 2 spaces), plus the PJS system

  • Site area:

  • Project design:

  • Actual implementation year: 2015

Automated parking system installation process for the MB Sunny project

Site layout

Challenges

A fire incident in the generator room’s heat exhaust system on Basement Level B3 on January 19 affected the delivery of equipment to the construction site and disrupted the project schedule.

Solution

Upon receiving the information, we immediately arrived at the site to assess the actual conditions following the incident.

  • All equipment remained unaffected by the fire due to the presence of partition walls.

  • The water level on the floor was 3 cm on the evening of January 19, causing no damage to the installed equipment.

The other equipment was unaffected.
The other equipment was unaffected.

Lessons learned

  • Improve construction safety awareness among all contractors and the workers and staff involved in the project.

  • The investor should also assign personnel to conduct inspections at the end of each work session to ensure the highest possible level of construction safety.

Construction progress

Challenges

Due to adverse weather conditions and storms in the East Sea, the transportation of goods was delayed. As a result, the equipment arrived at the construction site later than originally scheduled.

The equipment arrived at Ho Chi Minh City Port on December 15, 2014. Viet Chao Joint Stock Company is urgently completing the customs clearance procedures to transport the equipment to the construction site.

Solution

As the building was already operational, additional time was required to complete the necessary procedures, coordinate site access and construction activities, and arrange for several forklifts to operate at night. The contractor therefore proposed the following construction completion schedule and formally confirmed its commitment to meeting the agreed timeline:

  • Committed equipment delivery date to the construction site: Before December 24, 2014

  • Committed installation completion date: Before January 30, 2015

Lessons learned

The delay in meeting our commitments has affected the project’s use. We sincerely apologize to the investor, project management team, and supervision consultant, and respectfully ask for their understanding and consideration. We will make every effort to accelerate the installation process to make up for the delay outlined above.

Photos of automated parking system maintenance

MB Sunny project XIZI automated parking system interior
Inside the automated parking system
MB Sunny project automated parking system components
Some components inside the automated parking system
Inside the automated parking system
Inside the automated parking system
Some components inside the automated parking system
Some components inside the automated parking system

Viet Chao Joint Stock Company provides free 24/7 consultation to customers, offering the most suitable solutions for automated parking systems, elevators, escalators, BMUs, and more.

For consultation, please contact our hotlines: Sales – 0898 552 888 / Technical support – 0906 00 77 00.