Smart parking system at MB Sunny Building, District 1, Ho Chi Minh City
Viet Chao Joint Stock Company is honored to provide the automated parking system for the MB Sunny project at Sunny Building in District 1, Ho Chi Minh City.

-
Address: 259 Tran Hung Dao Street, District 1, Ho Chi Minh City
-
Brand/model: XIZI – 51 parking spaces (PSH2 – 49 spaces and MINI 31A – 1 system / 2 spaces)
MB Sunny project: project information
Challenges posed by the investor
-
Installation address: 259 Tran Hung Dao Street, District 1, Ho Chi Minh City
-
Project: Residential building combined with commercial services
-
Scope of work: Design, supply, and installation of the automated parking system
-
Implementation year: 2015
-
Investor requirements:
Viet Chao’s proposed solution
-
Brand: XIZI iParking
-
Model: Puzzle-type automated parking system PSH-2 and PJS2 lifting-type parking system
-
Parking capacity: XIZI – 51 spaces (PSH-2 – 49 spaces and MINI 31A – 1 system with 2 spaces), plus the PJS system
-
Site area:
-
Project design:
-
Actual implementation year: 2015
Automated parking system installation process for the MB Sunny project
Site layout
Challenges
A fire incident in the generator room’s heat exhaust system on Basement Level B3 on January 19 affected the delivery of equipment to the construction site and disrupted the project schedule.
Solution
Upon receiving the information, we immediately arrived at the site to assess the actual conditions following the incident.
-
All equipment remained unaffected by the fire due to the presence of partition walls.
-
The water level on the floor was 3 cm on the evening of January 19, causing no damage to the installed equipment.

Lessons learned
-
Improve construction safety awareness among all contractors and the workers and staff involved in the project.
-
The investor should also assign personnel to conduct inspections at the end of each work session to ensure the highest possible level of construction safety.
Construction progress
Challenges
Due to adverse weather conditions and storms in the East Sea, the transportation of goods was delayed. As a result, the equipment arrived at the construction site later than originally scheduled.
The equipment arrived at Ho Chi Minh City Port on December 15, 2014. Viet Chao Joint Stock Company is urgently completing the customs clearance procedures to transport the equipment to the construction site.
Solution
As the building was already operational, additional time was required to complete the necessary procedures, coordinate site access and construction activities, and arrange for several forklifts to operate at night. The contractor therefore proposed the following construction completion schedule and formally confirmed its commitment to meeting the agreed timeline:
-
Committed equipment delivery date to the construction site: Before December 24, 2014
-
Committed installation completion date: Before January 30, 2015
Lessons learned
The delay in meeting our commitments has affected the project’s use. We sincerely apologize to the investor, project management team, and supervision consultant, and respectfully ask for their understanding and consideration. We will make every effort to accelerate the installation process to make up for the delay outlined above.
Photos of automated parking system maintenance
![]() |
![]() |
![]() |
![]() |
Viet Chao Joint Stock Company provides free 24/7 consultation to customers, offering the most suitable solutions for automated parking systems, elevators, escalators, BMUs, and more.
For consultation, please contact our hotlines: Sales – 0898 552 888 / Technical support – 0906 00 77 00.