Automated parking system at Summer Tower (DeLaSol), District 4, Ho Chi Minh City
Summer (DeLaSol) project information
Amid rapid urbanization, the demand for parking facilities has become increasingly urgent, particularly in dynamic areas such as District 4. The Summer (DeLaSol) project, expected to contribute to Vietnam’s growing economic and financial hub, aims to provide a modern living environment and attract a vibrant residential community. Therefore, implementing a smart parking system in District 4 at DeLaSol represents both a technical challenge and an opportunity to enhance residents’ quality of life.
-

Panoramic view of the Summer (DeLaSol) project.
Developed by CapitaLand, DeLaSol (also known as Summer) is located on Ton That Thuyet Street. In addition to convenient transport connections, the project benefits from a wide range of nearby amenities.
Challenges and requirements from the investor
-
Installation address: Ton That Thuyet Street, District 4, Ho Chi Minh City
-
Project type: Residential development combined with commercial services
-
Scope of work: Design, supply, and installation of an automated parking system
-
Implementation year: 2018
-
Investor’s requirements:
The investor, CapitaLand, is one of Asia’s largest real estate groups. Headquartered in Singapore, this multinational company operates primarily in real estate, serviced residences, and real estate financial services, with a development focus on major cities across Asia-Pacific and Europe.
The project comprises 870 premium apartments. Therefore, the investor requires a large number of parking spaces that can meet the following requirements:
| Space optimization |
–Reduce space requirements by 60–70% compared with traditional parking facilities. –Make efficient use of underground space. -Free up more space for other project amenities. |
| Safety and security | The DeLaSol project is designed exclusively for residential apartments, with no officetel units, helping ensure residents’ security and privacy. Therefore, the smart parking system must also meet the following requirements:
– Surveillance camera system – Protect vehicles from collisions and avoidable accidents. – Ensure user safety. |
| Environmental friendliness | – Reduce vehicle emissions inside the basement.
– Save energy used for lighting and ventilation. – Contribute to the development of a green building. |
| Alignment with modern trends | – Meet the expectations of residents in luxury residential buildings.
– Enhance the value and prestige of the premium development. – Attract and retain customers through modern technology and equipment. |
Viet Chao’s solution
-
Brand: XIZI iParking
-
Model: PSH-2 puzzle-type automated parking system
-
Site area: 1.45 hectares
-
Project design: Three basement levels with over 300 parking spaces
-
Actual implementation year: 2019
-

Automated parking system
Installation process of the smart parking system in District 4
Site handover
Challenges
By February 13, 2023, we had completed the mechanical installation of 199 parking spaces for which the site had been handed over. However, 82 parking spaces had not yet been handed over to our team.
This issue persisted on May 13, 2023. By that date, Viet Chao had completed the mechanical installation of 272 parking spaces and the electrical installation and commissioning of 203 spaces. However, construction could not begin at 9 of the 281 parking spaces because the site areas had not yet been handed over to our team.
Solution
We notified the investor that the delayed handover of the remaining nine parking spaces would prevent us from guaranteeing the completion of 100% of the contracted work, as well as the scheduled inspection and acceptance of the entire system.
Nevertheless, Viet Chao committed to completing the installation of the 272 out of 281 parking spaces mentioned above in accordance with the plan before May 31, 2023.
We also informed the investor that any schedule delays or additional costs arising from the late handover of the remaining site areas would not be our responsibility.
Lessons learned
First, planning and managing the site handover schedule must be prioritized from the beginning of the project. This allows both parties to clearly define the timelines, conditions, and procedures for handing over each section, helping prevent delays and minimize their impact on the overall project schedule.
Second, timely communication and reporting of difficulties and obstacles are essential. We effectively kept the investor informed about the delayed site handover and its potential consequences for project progress.
Third, contingency plans and flexibility in implementation are necessary. Despite the challenge posed by the nine parking spaces that had not yet been handed over, Viet Chao remained committed to completing the work that could proceed—272 out of 281 parking spaces—on schedule. This demonstrates our sense of responsibility and ability to adapt to changing circumstances.
Construction schedule
Challenges
According to the original plan and contract, Viet Chao was scheduled to complete the installation of the 272 parking spaces handed over by May 31, 2023. However, at the investor’s request, the deadline for completing these 272 parking spaces was brought forward to May 15, 2023.
Solution
We respectfully requested that the investor confirm additional financial support to cover the extra costs incurred in meeting the accelerated construction schedule.
Lessons learned
An important lesson is the need for clear agreements and formal written confirmation of any changes to the project schedule. When the investor requested an accelerated deadline, moving the completion date from May 31 to May 15, Viet Chao responded professionally by proposing a solution to cover the additional costs incurred. This approach protects the contractor’s interests while demonstrating a cooperative attitude and a willingness to meet the investor’s requirements under reasonable conditions.
Advantages of installing a smart parking system in District 4
Equipment delivered according to the planned schedule
In accordance with the contract, we coordinated the order placement and delivery schedule with the manufacturer. The equipment for this project was divided into two shipments: the first shipment comprised nine 40-foot containers, while the second consisted of three 40-foot containers.
Although the delivery schedule depended on various factors, including customs clearance and the preparation of on-site storage areas, our close monitoring and proactive follow-up ensured that the equipment arrived at the project site in line with the schedule agreed upon in the signed contract.
Photos of the completed project
-

An orderly and space-efficient smart parking system
-

360-degree panoramic view of the DeLaSol (Summer) automated parking system
-

The system is currently operating very reliably and is regarded as one of Viet Chao’s flagship projects in southern Vietnam.
Warranty and maintenance of the Summer (DeLaSol) project parking system
![]() |
![]() |
With over 20 years of industry experience, Viet Chao has continuously developed and refined its smart parking solutions across a wide range of projects. Each project presents unique challenges, helping us gain valuable experience and continuously improve our technical capabilities and service quality. Customer satisfaction remains our benchmark for success.