Da Nang Times Square
In the context of urbanization, the construction of smart parking facilities in Da Nang offers an optimal solution for space utilization and an enhanced user experience. Located along My Khe Beach, the Da Nang Times Square project, developed by Kim Long Nam Group, boasts a prime location, impressive architecture, and smart amenities, setting a new standard for modern living.
Project information
With four frontages along the two major roads of Vo Nguyen Giap and Pham Van Dong, Da Nang Times Square benefits from convenient connections to the city center and the international airport. Featuring a complex of shopping centers, luxury hotels, and high-end apartments, the project is expected to attract a large number of residents and visitors. Therefore, the investor needs to implement a modern, convenient automated parking system to meet the growing demand for parking.
Challenges posed by the investor
-
Project address: Pham Van Dong and Vo Nguyen Giap streets, Son Tra District, Da Nang City
-
Building type: Residential and commercial complex
-
Scope of work: Design, supply, and installation of an automated parking system and vehicle access control system
-
Implementation period: Late 2024–2025

Viet Chao’s proposed solution
-
Brand: XIZI iParking
-
Model: PSH-2 puzzle-type automated parking system
-
Site area: Total area of 2.1 hectares, with a building density of 42% and a building footprint of 1.58 hectares
-
Total investment: VND 5.036 trillion
-
Actual implementation period: Kick-off date: September 26
Challenges during the construction of the smart parking facility in Da Nang
Site conditions
During project implementation, Viet Chao also faced several challenges, particularly regarding the delivery of equipment to the site:
Challenges:
- Transporting equipment by sea makes it difficult to determine the exact daily delivery schedule, especially when weather conditions are unfavorable.
- Most equipment and materials are imported as complete systems, making it impractical to deliver small quantities of materials to the construction site separately.
Solutions proposed by Viet Chao to minimize the impact of these challenges:
- As soon as Viet Chao receives official notification of the equipment arrival date, the company will conduct a detailed site survey to prepare for installation.
- A detailed inspection and acceptance plan will be communicated to the investor before installation begins, ensuring transparency and close coordination.
- Despite external factors affecting the detailed schedule, Viet Chao remains committed to ensuring that the overall project timeline is maintained.
Learn about the advantages during the construction of the smart parking facility in Da Nang here: Da Nang Times Square – Viet Chao Joint Stock Company
Video of the completed parking facility in operation
Viet Chao’s outstanding capabilities
From the early stages of the project, Viet Chao demonstrated a proactive approach, effective project management, and seamless coordination with relevant stakeholders. With a team of experienced engineers and experts in smart parking systems, we implemented the project systematically, from detailed design and equipment selection to well-organized construction. As a result, the smart parking facility at Da Nang Times Square was completed ahead of the schedule stipulated in the contract.
During project implementation, a technical issue arose regarding the material requirements for the bolts used in the system. The supervising consultant required the connecting bolts to be hot-dip galvanized. However, drawing on its technical expertise and hands-on experience across more than 50 projects, Viet Chao proactively conducted a detailed technical analysis of the advantages of each option under the coastal environmental conditions of this project:
- Electro-galvanizing produces a thin, bright, smooth coating with a more attractive finish. In particular, as this project is located near My Khe Beach, where salt concentrations are high, electro-galvanizing would be a more suitable option because it provides effective protection for small components and helps prevent localized corrosion.
- XIZI products comply with strict quality control procedures. Electro-galvanized bolts fully meet 100% of the system’s requirements for load-bearing capacity, wear resistance, and mechanical strength.
- Hot-dip galvanizing at high temperatures may increase the risk of hydrogen embrittlement in certain types of high-strength steel. Electro-galvanizing is performed at lower temperatures, reducing this risk and helping ensure product safety and service life.
Through continuous efforts and proven professionalism, Viet Chao has established itself as a leading provider of smart parking systems in Vietnam. We not only deliver advanced smart parking solutions but also provide investors with peace of mind and added value through effective project management, flexible problem-solving capabilities, and an unwavering commitment to the highest quality standards. Contact Vietchao via hotline 0898 55 28 88 get a consultation today.